|
Jan 2000
|
- RFP started |
|
Spring 2000
|
-Site visits to libraries to learn RFP pitfalls |
|
May 2000
|
- Legislature appropriates $8.1 million |
|
June 2000
|
- RFP finished |
|
July 2000
|
- RFP issued |
|
Sept 2000
|
- RFP responses due |
|
Oct 2000
|
- Initial scoring of RFP responses; vendor demos |
|
Nov 2000
|
- Site visits to libraries |
|
Dec 2000
|
- Final Scoring of vendors to determine first choice |
|
Jan 2001
|
- Contract negotiations begin |
|
Apr 2001
|
- Contract negotiations complete |
|
May 2001
|
- Order hardware for test system |
|
June 2001
|
- Install hardware for test system |
|
July 2001
|
- Initial System Overview Training for FCLA & Implementation Committee |
| - Install software for test system. | |
| - Pay vendor for training (1) | |
|
Aug 2001
|
- Implementation planning and decisions begun |
|
Sept 2001
|
- Data conversion planning and decisions begun |
|
Oct 2001
|
- Load sample data for testing |
| - Begin functional tests | |
|
Nov 2001
|
- Plan peak load simulation tests |
|
Dec 2001
|
- Complete functional tests |
|
Spring 2002
|
- Carry out peak load simulation tests |
| - Decide sequence of phased cut-overs | |
| - Order & install more hardware | |
| - Load lots more data for testing | |
| - Perform load simulations on local system | |
| - Partial payment to vendor | |
| - Training in all modules | |
|
June 2002
|
- Begin transition to new system |
| - Load full files | |
| - Clean-up of files as needed | |
| - More training in all modules | |
| - Pay vendor as more modules activated | |
|
June 2004
|
- Complete transition to new system |
| - Final payment to vendor |
(1) Use UF CLSI model for vendor payment.