LMS Transition Schedule - Hypothetical



Jan 2000
- RFP started
Spring 2000
 -Site visits to libraries to learn RFP pitfalls
May 2000
- Legislature appropriates $8.1 million
June 2000
- RFP finished
July 2000
- RFP issued
Sept 2000
- RFP responses due
Oct 2000
- Initial scoring of RFP responses; vendor demos
Nov 2000
- Site visits to libraries
Dec 2000
- Final Scoring of vendors to determine first choice
Jan 2001
- Contract negotiations begin
Apr 2001
- Contract negotiations complete
May 2001
- Order hardware for test system
 June 2001
- Install hardware for test system
July 2001
- Initial System Overview Training for FCLA & Implementation Committee
  - Install software for test system.
  - Pay vendor for training (1)
Aug 2001
- Implementation planning and decisions begun
Sept 2001
- Data conversion planning and decisions begun
Oct 2001
- Load sample data for testing
  - Begin functional tests
Nov 2001
- Plan peak load simulation tests
Dec 2001
- Complete functional tests
Spring 2002
- Carry out peak load simulation tests
  - Decide sequence of phased cut-overs
  - Order & install more hardware
  - Load lots more data for testing
  - Perform load simulations on local system
  - Partial payment to vendor
  - Training in all modules
June 2002
- Begin transition to new system
- Load full files
- Clean-up of files as needed
- More training in all modules
- Pay vendor as more modules activated
June 2004
- Complete transition to new system
- Final payment to vendor

 
    (1) Use UF CLSI model for vendor payment.